Public project record · Nepal
Development projects in Nepal
Explore projects reported by development organizations, donors, and public sources. Every record shows what is known, what is not reported, and where the evidence comes from.
- completed
Nepal: Making markets work for the conflict affected in Nepal
70%data completenessInvestment Project Financing
- Organization
- World Bank Nepal
- Budget
- USD 0
- Timeline
- Feb 17, 2012 → Jan 15, 2018
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Nepal: Community Action for Nutrition Project (Sunaula Hazar Din)
95%data completenessInvestment Project Financing. Implementing agency: Ministry of Federal Affairs and Local Development
- Organization
- World Bank Nepal
- Budget
- USD 40.0M
- Timeline
- Jun 26, 2012 → Jun 30, 2017
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Bridges Improvement and Maintenance Program
95%data completenessProgram-for-Results Financing. Implementing agency: Department of Roads
- Organization
- World Bank Nepal
- Budget
- USD 60.0M
- Timeline
- Jun 28, 2012 → Jul 15, 2017
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Nepal: Pilot Project for Seismic School Safety in the kathmandu
70%data completenessTechnical Assistance Loan
- Organization
- World Bank Nepal
- Budget
- USD 0
- Timeline
- Jul 23, 2012 → Jun 30, 2014
- Coverage
- Kathmandu, Bagmati
Good record·20 sources·Funded by World Bank Nepal - completed
Nepal PFM-MDTF Strengthening Civil Society Organizations' use of Social Accountability to improve PFM in Nepal
70%data completenessSpecific Investment Loan
- Organization
- World Bank Nepal
- Budget
- USD 0
- Timeline
- Aug 29, 2012 → Sep 30, 2014
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Additional Financing for the Project for Agriculture Commercialization and Trade
75%data completenessSpecific Investment Loan
- Organization
- World Bank Nepal
- Budget
- USD 40.0M
- Timeline
- Nov 15, 2012 → End not reported
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Kali Gandaki A Hydropower Plant Rehabilitation Project (KGAHPRP)
95%data completenessInvestment Project Financing. Implementing agency: Nepal Electricity Authority
- Organization
- World Bank Nepal
- Budget
- USD 27.3M
- Timeline
- May 15, 2013 → Jun 30, 2017
- Coverage
- Gandaki, Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Nepal: School Sector Reform Program Additional Financing
75%data completenessSpecific Investment Loan
- Organization
- World Bank Nepal
- Budget
- USD 100.0M
- Timeline
- May 15, 2013 → End not reported
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Second Additional Financing for the Poverty Alleviation FundII Project
75%data completenessSpecific Investment Loan
- Organization
- World Bank Nepal
- Budget
- USD 85.0M
- Timeline
- Jun 5, 2013 → End not reported
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Additional Financing for Nepal-India Electricity Transmission and Trade Project
75%data completenessSpecific Investment Loan
- Organization
- World Bank Nepal
- Budget
- USD 39.0M
- Timeline
- Jun 24, 2013 → End not reported
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Nepal-India Regional Trade And Transport Project
95%data completenessInvestment Project Financing. Implementing agency: Ministry of Industry, Commerce and Supplies, Ministry of Physical Infrastructure and Transport
- Organization
- World Bank Nepal
- Budget
- USD 99.0M
- Timeline
- Jun 28, 2013 → Nov 30, 2021
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Nepal: Pro-poor Urban Regeneration Pilot
70%data completenessInvestment Project Financing
- Organization
- World Bank Nepal
- Budget
- USD 0
- Timeline
- Oct 7, 2013 → Sep 30, 2018
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Adolescent Girls Employment Initiative II
85%data completenessInvestment Project Financing
- Organization
- World Bank Nepal
- Budget
- USD 640K
- Timeline
- Feb 3, 2014 → Dec 31, 2014
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
NP Rural Water Supply and Sanitation Improvement Project
95%data completenessInvestment Project Financing. Implementing agency: Rural Water Supply and Sanitation Fund Development Board, Ministry of Water Supply and Sanitation
- Organization
- World Bank Nepal
- Budget
- USD 72.0M
- Timeline
- May 29, 2014 → Jul 15, 2021
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Kabeli-A Hydro Electric Project
95%data completenessInvestment Project Financing. Implementing agency: Investment Board of Nepal, Ministry of Energy, Water Resources and Irrigation, Kabeli Energy Limited, Water and Energy Commission Secretariat
- Organization
- World Bank Nepal
- Budget
- USD 46.0M
- Timeline
- Jul 1, 2014 → Dec 30, 2019
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Nepal: Grid Solar and Energy Efficiency
95%data completenessInvestment Project Financing. Implementing agency: Nepal Electricity Authority
- Organization
- World Bank Nepal
- Budget
- USD 130.0M
- Timeline
- Dec 22, 2014 → Dec 15, 2022
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Higher Education Reforms Project
95%data completenessInvestment Project Financing. Implementing agency: University Grants Commission
- Organization
- World Bank Nepal
- Budget
- USD 65.0M
- Timeline
- Feb 19, 2015 → Dec 31, 2020
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
ROAD SAFETY SUPPORT PROJECT
85%data completenessInvestment Project Financing
- Organization
- World Bank Nepal
- Budget
- USD 7.5M
- Timeline
- Apr 8, 2015 → Jul 15, 2017
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
School Sector Reform Program Additional Financing
75%data completenessInvestment Project Financing
- Organization
- World Bank Nepal
- Budget
- USD 1164.0M
- Timeline
- Jan 13, 2016 → End not reported
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Nepal Third Financial Sector Stability Credit DPC3
75%data completenessDevelopment Policy Lending
- Organization
- World Bank Nepal
- Budget
- USD 100.0M
- Timeline
- Mar 2, 2017 → Mar 31, 2018
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - completed
Nepal School Sector Development Program
95%data completenessProgram-for-Results Financing. Implementing agency: Ministry of Education, Science and Technology
- Organization
- World Bank Nepal
- Budget
- USD 527.1M
- Timeline
- Mar 24, 2017 → Jul 16, 2022
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
MDTF Funding for Earthquake Housing Reconstruction Project
85%data completenessInvestment Project Financing
- Organization
- World Bank Nepal
- Budget
- USD 10.0M
- Timeline
- Aug 21, 2017 → Jul 30, 2022
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Nepal Livestock Sector Innovation Project
95%data completenessInvestment Project Financing. Implementing agency: Ministry of Agriculture and Livestock Development
- Organization
- World Bank Nepal
- Budget
- USD 80.0M
- Timeline
- Dec 7, 2017 → Jun 30, 2024
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
NP: Additional Financing Earthquake Housing Reconstruction
75%data completenessInvestment Project Financing
- Organization
- World Bank Nepal
- Budget
- USD 300.0M
- Timeline
- Dec 15, 2017 → End not reported
- Coverage
- Nepal
Good record·20 sources·Funded by World Bank Nepal - active
NP Modernization of Rani Jamara Kulariya Irrigation Scheme - Phase 2
95%data completenessInvestment Project Financing. Implementing agency: Department of Irrigation, Department of Agriculture within the Recipient's Ministry of Agriculture and Livestock Development, Department of Irrigation within the Recipient's Ministry of Energy, Water Resources and Irrigation
- Organization
- World Bank Nepal
- Budget
- USD 66.0M
- Timeline
- Mar 20, 2018 → Jul 15, 2025
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Second Bridges Improvement and Maintenance Program
95%data completenessProgram-for-Results Financing. Implementing agency: Ministry of Physical Infrastructure and Transport
- Organization
- World Bank Nepal
- Budget
- USD 133.0M
- Timeline
- Sep 26, 2018 → Jul 15, 2024
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Programmatic Fiscal and Public Financial Management Development Policy Credit ( II )
95%data completenessDevelopment Policy Lending. Implementing agency: Ministry of Finance
- Organization
- World Bank Nepal
- Budget
- USD 100.0M
- Timeline
- Jun 13, 2019 → Jun 30, 2020
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - active
Youth Employment Transformation Initiative Project
95%data completenessInvestment Project Financing. Implementing agency: Ministry of Labor, Employment and Social Security
- Organization
- World Bank Nepal
- Budget
- USD 120.0M
- Timeline
- Sep 12, 2019 → Jul 15, 2025
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Nepal Development Policy Financing with CAT DDO
95%data completenessDevelopment Policy Lending. Implementing agency: Ministry of Home Affairs (National Disaster Risk Reduction and Management Authority), Ministry of Health and Population, Ministry of Urban Development (Department of Urban Development and Building Construction), Ministry of Forests and Environment, Ministry of Finance (Main)
- Organization
- World Bank Nepal
- Budget
- USD 50.0M
- Timeline
- Mar 10, 2020 → Nov 30, 2024
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal - completed
Second Programmatic Energy Sector Development Policy Credit
95%data completenessDevelopment Policy Lending. Implementing agency: Ministry of Energy, Water Resources and Irrigation
- Organization
- World Bank Nepal
- Budget
- USD 100.0M
- Timeline
- Jun 2, 2020 → Jun 30, 2021
- Coverage
- Nepal
Complete record·20 sources·Funded by World Bank Nepal
How to read project data
A missing budget or date means the source did not provide it to Nepal Impact; it is not an estimate. Completeness measures the presence of core fields, while data confidence reflects source-level trust. Use the original source and the correction link on each project page for verification.