completed· Disaster Risk
Earthquake Response Cash Transfer Project
HelpAge's Unconditional Cash Transfer project initiated in response to 2015 Nepal earthquake in Gorkha, Sindhuli, Sindhupalchowk, Dolakha, Makwanpur districts reaching 5,000 beneficiaries.
Not reported budget·USD 516K disbursed·HelpAge International implementer·Dolakha, makawanpur location·May 27, 2015 → Jul 26, 2015 timeline
Overview
About this project
HelpAge's Unconditional Cash Transfer project initiated in response to 2015 Nepal earthquake in Gorkha, Sindhuli, Sindhupalchowk, Dolakha, Makwanpur districts reaching 5,000 beneficiaries.
Record quality
85% complete
2 sources · confidence 65%Not reported by the available sources: budget. This is intentionally shown as unavailable rather than estimated.
Report an update or correctionProgress
—Plan
Implementation
Outcomes
Alignment
SDG focus
No SDGs tagged.