completed
Audit of the Inclusive Growth Programme in Nepal
An independent Monitoring and Results Measurement Coordinator will be procured through international bidding process.
USD 43K budget·USD 30K disbursed·Ministry of Foreign Affairs, Denmark implementer·Nepal location·Dec 16, 2016 → Feb 13, 2020 timeline
Overview
About this project
An independent Monitoring and Results Measurement Coordinator will be procured through international bidding process.
Record quality
90% complete
Not reported by the available sources: sectors. This is intentionally shown as unavailable rather than estimated.
Report an update or correctionProgress
69%- Plan
- Implementation
- Outcomes
Alignment
SDG focus
No SDGs tagged.